Contractor Resources

Procurement Timeline

2025

2026

2027

2028

2029

2030

Bid Package One: 2025 May-June

Bid Package Two: Q3 2025 August - Sept

Bid Package Three: Q4 2025

Bid Package Four: Q2 2026

Bid Package Five: Q3 2026

Phase I Construction Start: Q1 2027

Phase II Construction Start: Q1 2028

Phase I Construction Complete: Q2 2029

Phase II Construction Complete: Q3 2030

Upcoming Bid Opportunities

Bid Package 1, May/June 2025 75% SD (Design Build/MEPF)

Click to view San Francisco City Partner post: EXT CII | MB4E Phase 1 MEPF D/B Bid Package

Bid Package 2, Q3 2025 50% DD (Demo, Steel Piles, Earthwork, Exterior Skin)

Bid Package 3, Q4 2025 100% DD (Tower Crane, Personnel Hoist, EBM, Elevator, Shoring/Ex, Site ​Utilities)

LBE, SBE, Trade Partner Event, 3/25/25

On March 25, 2025 the MB4E team hosted an LBE, SBE, Trade Partner Outreach Meeting, sharing the project's procurement timeline and bidding opportunities.​​ Below is the presentation featured at the event.

MB4E LBE, SBE, Trade Partner Outreach Meeting. Ariel image of housing development site.

Additional Resources for First-time Bidders

Swinerton Subcontractor Prequalification

https://swinerton.com/subcontractor-prequalification/

subcontractorprequal@swinerton.com

Swinerton Subcontractor Required Documents

Required documents for subcontractor prequalification.

https://swinerton.com/subcontractor-prequalification/#documents

Swinerton New Subcontractors

Information for Non-East Coast new and existing contractors.

https://swinerton.com/subcontractor-prequalification/#east

Swinerton Prequalification Point of Contact

For questions about prequalification, please contact Mick Penn, Director of Community Relations, at MPenn@swinerton.com.

Merriwether & Williams: City and County of San Francisco – Contractor Development Program

The City and County of San Francisco (CCSF) created the Contractor Development Program in 1997 to increase participation of underrepresented San Francisco Bay Area contractors in city and county construction projects. CCSF’s Contractor Development Program offers local contractors a range of services, from technical support to contract financing assistance.

Program services are sponsored by the City and County of San Francisco and, with the exception of a $500 participation fee for the preparation of business financial statements, all services are provided at no charge to participating Contractors.

https://imwis.com/services/contractor-bonding-development-programs/city-and-county-of-san-francisco/

bottom of page